Aurora Organic Dairy

  • 30,000 sf fluid milk processing facility
  • Total project duration was seven months from ground-breaking to milk production
  • To speed construction, the process tanks were set in place upon completion of the foundations and the remaining structure was completed around the tanks
  • Seamless integration of all phases was accomplished through early teamwork planning to coordinate processes, packaging, controls, refrigeration and utilities

Project Specs

Project Type
New Construction
Project Size
30,000 sf
Location
Platteville, Colorado